PMI-ACP Question #204: Real Exam Question with Answer & Explanation
The correct answer is C: Product Team. Value Point estimating is the process of assigning relative business value to user stories or backlog items. This is performed by the Product Team (business stakeholders, product owners, or product managers) because they have the domain knowledge and business context needed to de
Question
Who performs Value Point estimating?
Options
- AFinance Team
- BScrum Team
- CProduct Team
- DDevelopment Team
Explanation
Value Point estimating is the process of assigning relative business value to user stories or backlog items. This is performed by the Product Team (business stakeholders, product owners, or product managers) because they have the domain knowledge and business context needed to determine the relative worth of each feature. Story Point estimation (effort) is done by the Development Team, but value estimation is a business decision that belongs to the product side of the organization.
Topics
Community Discussion
No community discussion yet for this question.