PMI-ACP · Question #195
PMI-ACP Question #195: Real Exam Question with Answer & Explanation
The correct answer is A: 7. Number of iterations = Total story points / Velocity = 27 / 4 = 6.75. Since you cannot have a partial iteration, you round up to 7 iterations. The team size (4 developers) is a distractor; velocity already accounts for the team's collective output per iteration. Always round up b
Question
Assuming one-week iterations and a team of four developers, how many iterations will it take the team to complete a project with 27 story points if they have a velocity of 4?
Options
- A7
- B4
- C6
- D24
Explanation
Number of iterations = Total story points / Velocity = 27 / 4 = 6.75. Since you cannot have a partial iteration, you round up to 7 iterations. The team size (4 developers) is a distractor; velocity already accounts for the team's collective output per iteration. Always round up because partial iterations still require a full timebox to complete remaining work.
Topics
Community Discussion
No community discussion yet for this question.