nerdexam
PMI

PMI-ACP · Question #195

Assuming one-week iterations and a team of four developers, how many iterations will it take the team to complete a project with 27 story points if they have a velocity of 4?

Sign in or unlock PMI-ACP to reveal the answer and full explanation for question #195. The question stem and answer options stay visible for context.

Submitted by zhang_li· Apr 18, 2026Adaptive Planning

Question

Assuming one-week iterations and a team of four developers, how many iterations will it take the team to complete a project with 27 story points if they have a velocity of 4?

Options

  • A7
  • B4
  • C6
  • D24

Unlock PMI-ACP to see the answer

You've previewed enough free PMI-ACP questions. Unlock PMI-ACP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Agile Estimation#Velocity Calculation#Iteration Planning#Project Duration
Full PMI-ACP Practice