Agile Teams use Planning Poker for estimation. Which of the following is NOT true about Planning Poker?

Options

  • AIt combines expert opinion, analogy, and disaggregation into an enjoyable approach to estimating
  • BParticipants include all of the developers on the team
  • CThe team for Planning Poker should not exceed more than 10 participants
  • DThe highest estimate is considered the final estimate

Unlock PMI-ACP to see the answer

You've previewed enough free PMI-ACP questions. Unlock PMI-ACP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Planning Poker#Estimation#Agile Techniques