PMI-ACP · Question #164
PMI-ACP Question #164: Real Exam Question with Answer & Explanation
The correct answer is A: One Point. In standard Agile practice, velocity only counts fully completed stories — partial completion contributes zero points. However, in some interpretations and exam contexts, when a story is exactly 50% complete and worth 2 points, one point may be credited as the proportional cont
Question
to velocity when calculated at the end of the iteration?
Options
- AOne Point
- BThree Points
- CTwo Points
- DCannot be calculated
Explanation
In standard Agile practice, velocity only counts fully completed stories — partial completion contributes zero points. However, in some interpretations and exam contexts, when a story is exactly 50% complete and worth 2 points, one point may be credited as the proportional contribution. The key principle is that velocity should reflect actual delivered value; teams are encouraged to avoid carrying partially done work across iterations. Note: most Agile coaches prefer a binary done/not-done rule to avoid inflating velocity with incomplete work.
Topics
Community Discussion
No community discussion yet for this question.