The correct answer is B: The early and continuous delivery of valuable software, providing increased visibility and the. A core Agile benefit for stakeholders is frequent, incremental delivery of working software from early in the project. This gives stakeholders visibility into real progress (not just reports), the opportunity to inspect and adapt based on what they see, and the ability to reprior
Question
What key benefits might stakeholders realize from an Agile approach?
Options
- AThe ability to bypass the change-management process, inserting new requirements and
- BThe early and continuous delivery of valuable software, providing increased visibility and the
- CIncreased access to the project and less reliance on formal reports and status meetings to
- DThe team's flexibility to make changes mid-iteration as business needs or priorities change,
Explanation
A core Agile benefit for stakeholders is frequent, incremental delivery of working software from early in the project. This gives stakeholders visibility into real progress (not just reports), the opportunity to inspect and adapt based on what they see, and the ability to reprioritize or change direction based on evolving business needs. Option A describes bypassing change management, which Agile does not advocate. Option C and D describe secondary benefits but do not capture the primary, most valued stakeholder benefit that Agile is built around.