nerdexam
PMIPMI

PMI-ACP · Question #125

PMI-ACP Question #125: Real Exam Question with Answer & Explanation

The correct answer is B: Schedule a meeting with them after a Daily Scrum meeting to explore and resolve the issue.. Daily Scrum meetings are time-boxed and meant for synchronization, not conflict resolution. The appropriate action is to schedule a dedicated follow-up meeting with the individuals involved to explore and resolve the friction privately and constructively. Attempting to resolve it

Submitted by fernanda_arg· Apr 18, 2026Team Performance

Question

meetings. The next step should be to:

Options

  • AAttempt to resolve the problem directly and immediately during a Daily Scrum meeting.
  • BSchedule a meeting with them after a Daily Scrum meeting to explore and resolve the issue.
  • CIgnore the friction because a self-organizing team must sort out team conflict issues.
  • DAsk for new resources to replace them before the friction undermines the team's productivity.

Explanation

Daily Scrum meetings are time-boxed and meant for synchronization, not conflict resolution. The appropriate action is to schedule a dedicated follow-up meeting with the individuals involved to explore and resolve the friction privately and constructively. Attempting to resolve it mid-Daily Scrum (A) disrupts the meeting's purpose. Ignoring conflict (C) is harmful — self-organization does not mean unmanaged dysfunction. Requesting new resources (D) is premature and extreme before attempting resolution.

Topics

#Team Conflict#Daily Scrum#Agile Facilitation#Team Collaboration

Community Discussion

No community discussion yet for this question.

Full PMI-ACP PracticeBrowse All PMI-ACP Questions