nerdexam
PMIPMI

PMI-ACP · Question #113

PMI-ACP Question #113: Real Exam Question with Answer & Explanation

The correct answer is A: Burndown chart. A burndown chart tracks remaining work (story points or tasks) against time across a sprint, giving the team and stakeholders real-time visibility into whether the sprint goal is on track. It is the standard Agile/Scrum tool for intra-sprint progress transparency. A Gantt chart i

Submitted by klara.se· Apr 18, 2026Value-driven Delivery

Question

A development team has finished identifying the tasks they will be accountable for during the next sprint. Which of the following tools best provides transparency into the progress throughout the sprint?

Options

  • ABurndown chart
  • BGantt chart
  • CHours expended chart
  • DManagement baseline chart

Explanation

A burndown chart tracks remaining work (story points or tasks) against time across a sprint, giving the team and stakeholders real-time visibility into whether the sprint goal is on track. It is the standard Agile/Scrum tool for intra-sprint progress transparency. A Gantt chart is a waterfall scheduling tool. An 'hours expended' chart shows effort spent but not remaining work or completion status. A 'management baseline chart' is not a standard Agile artifact.

Topics

#Burndown chart#Sprint tracking#Agile metrics#Transparency

Community Discussion

No community discussion yet for this question.

Full PMI-ACP PracticeBrowse All PMI-ACP Questions