PHR · Question #34

An organization would like to bid on a project, but they don't have enough employees available to complete the work. The organization approaches a competitor with the opportunity to partner on the…

Sign in or unlock PHR to reveal the answer and full explanation for question #34. The question stem and answer options stay visible for context.

Business Management

Question

An organization would like to bid on a project, but they don't have enough employees available to complete the work. The organization approaches a competitor with the opportunity to partner on the project to win the work. What type of risk response is used in this instance?

Options

  • ASharing
  • BMitigation
  • CEnhancing
  • DTransference

Unlock PHR to see the answer

You've previewed enough free PHR questions. Unlock PHR for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#risk sharing#risk response strategies#project risk management#organizational partnerships