PGMP · Question #528

The program manager takes over a poorly performing program. After a review of the documentation and interviews with the program sponsor, stakeholders, and program constituents, the program manager…

The correct answer is A. Assess the program schedule and determine how to maintain all projects and components within. When inheriting a misaligned program, the first action must be a thorough assessment of the program schedule and all component projects. This diagnostic step reveals the current state, interdependencies, resource commitments, and what can realistically be maintained - providing…

Strategic Program Management

Question

The program manager takes over a poorly performing program. After a review of the documentation and interviews with the program sponsor, stakeholders, and program constituents, the program manager realizes that the program is not aligned with the corporate/organizational goals. The program manager must realign the constituent projects and components to meet the program's needs. What action should the program manager take to realign the program?

Options

  • AAssess the program schedule and determine how to maintain all projects and components within
  • BDiscuss the situation with the program stakeholders and let them decide which projects to
  • CDiscuss the situation with the program sponsor(s) and let the sponsor(s) make the decision as to
  • DDevelop a change request to present to the governance board, accelerate some projects, close

How the community answered

(26 responses)
  • A
    65% (17)
  • B
    4% (1)
  • C
    12% (3)
  • D
    19% (5)

Explanation

When inheriting a misaligned program, the first action must be a thorough assessment of the program schedule and all component projects. This diagnostic step reveals the current state, interdependencies, resource commitments, and what can realistically be maintained - providing the data foundation for any subsequent realignment decisions. Proposing a change request to the governance board (D) or recommending project closures without this analysis is premature and uninformed. Deferring the decision to stakeholders (B) or the sponsor (C) without first providing a data-driven assessment fails the program manager's analytical responsibility.

Topics

#Program Strategic Alignment#Program Realignment#Program Performance#Program Schedule Management