PGMP · Question #512

PGMP Question #512: Real Exam Question with Answer & Explanation

Sign in or unlock PGMP to reveal the answer and full explanation for question #512. The question stem and answer options stay visible for context.

Program Governance

Question

Component project managers create project management plans for all component projects in a program. The program manager notices that some project managers prefer one status report template, while others prefer another. How should the program manager decide which template is appropriate?

Options

  • AReview the issue with the program management office (PMO) to determine which template to use.
  • BReview the issue with the project managers and come to mutual agreement on which template to
  • CMeet with the program governance board to select an appropriate template.
  • DAllow the component project managers to use their preferred templates.

Unlock PGMP to see the answer

You've previewed enough free PGMP questions. Unlock PGMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Program Standardization#Communication Management#Team Collaboration#Program Governance
Full PGMP PracticeBrowse All PGMP Questions