nerdexam
PMI

PGMP · Question #511

A program manager evaluates conflicting stakeholder demands associated with cost, schedule, and intended benefits. The implementation team has a strong interest in cost and schedule, and a limited int

The correct answer is D. Conduct a stakeholder meeting to allow everyone to state their priorities.. When stakeholders have fundamentally different and conflicting priorities - the implementation team focused narrowly on cost and schedule, the client focused exclusively on benefits - the most effective initial action is to convene a stakeholder meeting where each group can artic

Stakeholder Management

Question

A program manager evaluates conflicting stakeholder demands associated with cost, schedule, and intended benefits. The implementation team has a strong interest in cost and schedule, and a limited interest in the benefits being produced. The client is only focused on benefits. Which of the following actions should the program manager take?

Options

  • AFocus on the internal stakeholders to ensure cost and schedule objectives are achieved.
  • BBalance stakeholder needs through the use of trade-offs among the stakeholder groups.
  • CFocus on the external stakeholders to ensure the intended benefits are achieved.
  • DConduct a stakeholder meeting to allow everyone to state their priorities.

How the community answered

(34 responses)
  • A
    12% (4)
  • B
    3% (1)
  • C
    6% (2)
  • D
    79% (27)

Explanation

When stakeholders have fundamentally different and conflicting priorities - the implementation team focused narrowly on cost and schedule, the client focused exclusively on benefits - the most effective initial action is to convene a stakeholder meeting where each group can articulate their priorities. This creates shared visibility and mutual understanding of each party's constraints and goals. Without this shared context, any trade-offs the program manager makes unilaterally (as in options A, B, or C) may be uninformed or perceived as biased. Option A (focusing on internal stakeholders) ignores client needs. Option C (focusing on external stakeholders) ignores execution realities. Option B (balancing through trade-offs) is ultimately the right outcome, but the program manager cannot make meaningful trade-offs without first facilitating open dialogue among stakeholders. The meeting in option D creates the foundation for informed, transparent, and accepted trade-off decisions.

Topics

#Stakeholder Management#Conflict Resolution#Program Communication#Prioritization

Community Discussion

No community discussion yet for this question.

Full PGMP Practice