A new program component provides an opportunity to enhance program outcomes. What does the program manager use to document and monitor the opportunity?

The correct answer is B. Program scope management plan. A new program component that enhances program outcomes represents a change to the program's scope - what the program will deliver. The Program Scope Management Plan (B) governs how scope changes, additions, and enhancements are documented, approved, and monitored throughout the p

Program Lifecycle Management - Scope Management

Question

A new program component provides an opportunity to enhance program outcomes. What does the program manager use to document and monitor the opportunity?

Options

  • AProgram risk register
  • BProgram scope management plan
  • CProgram risk management plan
  • DComponent project risk register

How the community answered

(39 responses)
  • A
    5% (2)
  • B
    74% (29)
  • C
    8% (3)
  • D
    13% (5)

Explanation

A new program component that enhances program outcomes represents a change to the program's scope - what the program will deliver. The Program Scope Management Plan (B) governs how scope changes, additions, and enhancements are documented, approved, and monitored throughout the program lifecycle. While opportunities are sometimes tracked in risk registers (A, D) in a risk management context, the addition of a new component that changes program deliverables is fundamentally a scope matter governed by the scope management plan. The Program Risk Management Plan (C) defines the approach to risk management processes, not a register for documenting specific items. The scope management plan is the correct artifact for documenting and monitoring component-level opportunities that affect program outcomes.

Topics

#Program Scope Management#Program Components#Benefits Realization#Program Planning