PGMP · Question #400

You are a Project Manager managing the building of a restaurant. As the electrical wiring is being installed, you cannot find a building permit. As the Project Manager, to whom do you report this viol

The correct answer is B. The local city authority. Building permits for construction projects - including electrical work - are issued and regulated by local city (municipal) authorities (B). City building departments enforce construction codes and permit requirements within their jurisdiction. This is a local regulatory matter,

Program Governance

Question

You are a Project Manager managing the building of a restaurant. As the electrical wiring is being installed, you cannot find a building permit. As the Project Manager, to whom do you report this violation?

Options

  • AThe construction company
  • BThe local city authority
  • CThe local county authority
  • DThe state authority

How the community answered

(19 responses)
  • B
    95% (18)
  • D
    5% (1)

Explanation

Building permits for construction projects - including electrical work - are issued and regulated by local city (municipal) authorities (B). City building departments enforce construction codes and permit requirements within their jurisdiction. This is a local regulatory matter, not a county (C), state (D), or contractor-level (A) issue. Reporting to the construction company (A) is internal and does not address the regulatory violation. County and state authorities generally do not manage municipal building permits. The local city authority is the correct regulatory body to report the missing permit to, as they have jurisdiction over local construction compliance.

Topics

#Regulatory Compliance#Program Governance#Risk Management#Legal Adherence