Which of the following documents provides the mandate to execute the program within a certain timeline and also presents milestones for the delivery of products or incremental benefits?
The correct answer is A. Program charter. The program charter is the foundational authorization document for a program. It formally authorizes the program to exist, provides the mandate (authority) to execute it, defines the timeline, and outlines key milestones for delivering products or incremental benefits. It is…
Question
Which of the following documents provides the mandate to execute the program within a certain timeline and also presents milestones for the delivery of products or incremental benefits?
Options
- AProgram charter
- BProgram WBS
- CProgram risk register
- DProgram architecture baseline
How the community answered
(26 responses)- A88% (23)
- B8% (2)
- D4% (1)
Explanation
The program charter is the foundational authorization document for a program. It formally authorizes the program to exist, provides the mandate (authority) to execute it, defines the timeline, and outlines key milestones for delivering products or incremental benefits. It is analogous to a project charter but at the program level. The program WBS breaks down deliverables, the risk register tracks risks, and the architecture baseline defines the technical structure - none of these provide the mandate or milestones in the way the charter does.