nerdexam
PMI

PGMP · Question #119

Mary Anne is the program manager for her organization. In her program there are six projects. One of the projects in her program has been performing well. It is on schedule and has no cost or schedule

The correct answer is A. The program scope has changed.. When a program is terminated, all of its constituent projects should also be terminated - even those performing well - because the program's strategic justification no longer exists. The most likely reason for program termination is that the program scope has changed (e.g., the b

Strategic Program Management

Question

Mary Anne is the program manager for her organization. In her program there are six projects. One of the projects in her program has been performing well. It is on schedule and has no cost or schedule variances. Mary Anne has decided, however, that her program needs to be terminated. Which one of the following is a likely reason why the project should be terminated?

Options

  • AThe program scope has changed.
  • BThe scope is not being met as planned due to scope creep.
  • CThe project resources are not completing their project tasks as assigned.
  • DThe project scope has changed from the original intent of the project

How the community answered

(45 responses)
  • A
    76% (34)
  • B
    4% (2)
  • C
    13% (6)
  • D
    7% (3)

Explanation

When a program is terminated, all of its constituent projects should also be terminated - even those performing well - because the program's strategic justification no longer exists. The most likely reason for program termination is that the program scope has changed (e.g., the business need shifted, the strategy was realigned, or the expected benefits are no longer relevant). Individual project performance is irrelevant if the overarching program no longer serves the organization's goals. Options B, C, and D describe project-level problems, which would not explain terminating a project that is explicitly described as performing well.

Topics

#Program Termination#Strategic Alignment#Program Scope Management#Program Lifecycle

Community Discussion

No community discussion yet for this question.

Full PGMP Practice