PFMP · Question #8
Which of the following are the tools and techniques for "Develop Portfolio Performance Management Plan"? (Choose two.)
The correct answer is B. Capability and Capacity Analysis D. PMIS. Capability and Capacity Analysis and PMIS are the tools and techniques defined for the Develop Portfolio Performance Management Plan process.
Question
Which of the following are the tools and techniques for "Develop Portfolio Performance Management Plan"? (Choose two.)
Options
- AQuantitative and Qualitative Analyses
- BCapability and Capacity Analysis
- CBenefit Realization Analysis
- DPMIS
How the community answered
(30 responses)- A7% (2)
- B90% (27)
- C3% (1)
Why each option
Capability and Capacity Analysis and PMIS are the tools and techniques defined for the Develop Portfolio Performance Management Plan process.
Quantitative and Qualitative Analyses are used in other portfolio processes such as risk identification and scoring, and are not specifically defined T&Ts for this process.
Capability and Capacity Analysis assesses the organization's ability to deliver against portfolio performance targets, which is essential input when defining the metrics and thresholds in the performance management plan.
Benefit Realization Analysis is associated with portfolio value management processes, not the Develop Portfolio Performance Management Plan process.
The Portfolio Management Information System (PMIS) provides the technology and data infrastructure needed to collect, analyze, and report on the portfolio performance metrics defined in the plan.
Concept tested: Develop Portfolio Performance Management Plan tools and techniques