PMIPMI
PFMP · Question #62
PFMP Question #62: Real Exam Question with Answer & Explanation
The correct answer is C: Portfolio sponsors, portfolio stakeholders, functional managers. See the full explanation below for the reasoning.
Portfolio Performance Management
Question
When sharing portfolio performance reports, who could be the intended recipients?
Options
- AProject sponsors, portfolio manager, PMO, contracting officer
- BProject sponsors, portfolio manager, PMO
- CPortfolio sponsors, portfolio stakeholders, functional managers
- DProject team, project team members, SMEs
Topics
#Portfolio Performance Reporting#Portfolio Stakeholder Management#Portfolio Communication#Portfolio Governance
Community Discussion
No community discussion yet for this question.