PFMP · Question #553
You are managing a complex portfolio with high risk levels due to emerging technological breakthroughs and a short benefit window to market your product. You know that managing risk is key to…
The correct answer is D. Portfolio Reports. When a risk event occurs in a portfolio, it must be reported through Portfolio Reports, which are the formal mechanism for communicating risk occurrences to stakeholders and governance bodies.
Question
You are managing a complex portfolio with high risk levels due to emerging technological breakthroughs and a short benefit window to market your product. You know that managing risk is key to success and you are coaching your team on the same. A major risk has recently occurred and the risk owner came to you asking advise on how to report it. what would you advise her?
Options
- APortfolio Process Assets
- BRisk Register
- CPortfolio Organizational Assets
- DPortfolio Reports
How the community answered
(16 responses)- A13% (2)
- B6% (1)
- C6% (1)
- D75% (12)
Why each option
When a risk event occurs in a portfolio, it must be reported through Portfolio Reports, which are the formal mechanism for communicating risk occurrences to stakeholders and governance bodies.
Portfolio Process Assets are repositories of historical information, templates, and lessons learned - they are not used to report an active risk occurrence in real time to decision-makers.
The Risk Register is used to track and plan for risks in advance, but it is not the communication mechanism for reporting a risk event to stakeholders after it has materialized.
Portfolio Organizational Assets include policies, procedures, and governance frameworks - they provide guidance but are not where risk occurrences are actively reported.
Portfolio Reports are the designated communication vehicle for conveying portfolio status, including risk events that have materialized. When a major risk occurs, the risk owner reports it through Portfolio Reports to keep stakeholders informed, support governance decisions, and ensure formal documentation of the event. This structured reporting channel provides the transparency and escalation path required at the portfolio level.
Concept tested: Portfolio risk event reporting and communication
Source: https://www.pmi.org/pmbok-guide-standards/foundational/standard-for-portfolio-management