An urgent review meeting was set due to the discovery of multiple risks which can have drastic effects on the portfolio. As a result of the meeting, it was agreed to increase the portfolio budget…

The correct answer is A. Portfolio Management Plan updates. A governance decision to increase the portfolio budget and add resources to address new risks requires a formal update to the Portfolio Management Plan to reflect the revised management approach.

Portfolio Governance

Question

An urgent review meeting was set due to the discovery of multiple risks which can have drastic effects on the portfolio. As a result of the meeting, it was agreed to increase the portfolio budget and add more resources in order to manage the new risks. Which of the following documents needs to be updated as a result of this decision?

Options

  • APortfolio Management Plan updates
  • BPortfolio Reports
  • CPortfolio updates
  • DPortfolio Process Assets updates

How the community answered

(29 responses)
  • A
    79% (23)
  • B
    14% (4)
  • C
    3% (1)
  • D
    3% (1)

Why each option

A governance decision to increase the portfolio budget and add resources to address new risks requires a formal update to the Portfolio Management Plan to reflect the revised management approach.

APortfolio Management Plan updatesCorrect

The Portfolio Management Plan is the authoritative document governing how the portfolio is managed, including resource allocation policies and risk response strategies. Any approved change to funding levels or resource assignments resulting from a governance decision must be formally recorded in the Portfolio Management Plan to keep it current, authoritative, and aligned with the steering committee's direction.

BPortfolio Reports

Portfolio Reports are communication outputs that reflect current portfolio status; they document what has happened but are not updated to authorize or record changes to the management approach.

CPortfolio updates

Portfolio updates refer to changes in portfolio component composition or categorization, not to changes in the management plan that governs how the portfolio operates.

DPortfolio Process Assets updates

Portfolio Process Assets capture historical information, templates, and lessons learned; they are not the primary document updated in response to a new governance decision about budget and resources.

Concept tested: Portfolio Management Plan update triggers from governance decisions

Source: https://www.pmi.org/pmbok-guide-standards/foundational/portfolio-management

Topics

#Portfolio Management Plan#Portfolio Governance#Portfolio Risk Management#Portfolio Financial Management