One of your team members came to you asking about the risk "Watch List"; he heard this term in a meeting on risk analysis and did not know what it meant. What will your advice to your team member be?
The correct answer is A. Watch Lists include the risks with low probability and low impact that do not require further. In risk management (covered in PMI standards including PMBOK and Portfolio Management), a Watch List contains risks that have been assessed as low probability AND low impact - meaning they don't currently warrant active response planning or resource allocation. These risks are…
Question
One of your team members came to you asking about the risk "Watch List"; he heard this term in a meeting on risk analysis and did not know what it meant. What will your advice to your team member be?
Options
- AWatch Lists include the risks with low probability and low impact that do not require further
- BWatch Lists include the risks with low probability and high impact that needs to be watched
- CWatch Lists include the risks with high probability and low impact that needs to be watched
- DWatch Lists include the risks with high probability and high impact that needs to be watched
How the community answered
(22 responses)- A91% (20)
- B5% (1)
- D5% (1)
Explanation
In risk management (covered in PMI standards including PMBOK and Portfolio Management), a Watch List contains risks that have been assessed as low probability AND low impact - meaning they don't currently warrant active response planning or resource allocation. These risks are not ignored but are monitored passively to ensure they don't escalate. If a risk has high impact (even with low probability), it typically receives a formal response plan due to the potential consequences. The Watch List is specifically for risks that fall below the threshold of requiring immediate action, making option A the precise and correct definition.