You are managing a large portfolio and know that you will need to constantly show the progress and status of the portfolio in meeting. For this you have developed a robust roadmap using BI tools. The
The correct answer is A. High-level prioritization mapping of the portfolio. The Portfolio Roadmap is defined as a high-level prioritization mapping of the portfolio - it shows which components are approved, their relative priority, and their planned timing/sequencing across a timeline. It is a strategic visualization tool that communicates what the portf
Question
You are managing a large portfolio and know that you will need to constantly show the progress and status of the portfolio in meeting. For this you have developed a robust roadmap using BI tools. The Portfolio Roadmap is an important document that is referenced throughout the portfolio life cycle. Which of the following is correct regarding the Portfolio Roadmap purpose and focus?
Options
- AHigh-level prioritization mapping of the portfolio
- BCorresponds to the means to the "to-be" vision
- CCan be used to influence the portfolio's success
- DForecasts how and when the portfolio will deliver value to the organization
How the community answered
(23 responses)- A91% (21)
- C4% (1)
- D4% (1)
Explanation
The Portfolio Roadmap is defined as a high-level prioritization mapping of the portfolio - it shows which components are approved, their relative priority, and their planned timing/sequencing across a timeline. It is a strategic visualization tool that communicates what the portfolio contains and when things will happen, not a detailed execution plan. Option B (means to the 'to-be' vision) describes the portfolio itself or strategic plan. Option C (influence success) is too vague and generic. Option D (forecasts value delivery) is more characteristic of a benefits realization plan. The roadmap's primary role is prioritization mapping.