PFMP · Question #423

There was a change in your portfolio to speed up things resulting in the addition of new components. In order to update the new vision, dependencies and timeline for the components, you should…

The correct answer is A. Portfolio Roadmap. The Portfolio Roadmap is the document that should be updated when new components are added and the vision, dependencies, and timeline need to reflect those changes. The Portfolio Roadmap is a chronological representation of the portfolio's intended direction, showing…

Strategic Alignment

Question

There was a change in your portfolio to speed up things resulting in the addition of new components. In order to update the new vision, dependencies and timeline for the components, you should update which of the following?

Options

  • APortfolio Roadmap
  • BPortfolio Charter
  • CPortfolio Strategic Plan
  • DPortfolio Management Plan

How the community answered

(36 responses)
  • A
    83% (30)
  • B
    3% (1)
  • C
    11% (4)
  • D
    3% (1)

Explanation

The Portfolio Roadmap is the document that should be updated when new components are added and the vision, dependencies, and timeline need to reflect those changes. The Portfolio Roadmap is a chronological representation of the portfolio's intended direction, showing interdependencies between components, programs, and projects, along with high-level milestones and timelines. When a change (such as accelerating timelines or adding new components) occurs, the roadmap is updated to reflect the new 'to-be' state. The Portfolio Charter authorizes the portfolio overall. The Portfolio Strategic Plan defines strategic direction. The Portfolio Management Plan governs how the portfolio is managed-none of these primarily capture timeline and dependency updates the way the Roadmap does.

Topics

#Portfolio Roadmap#Portfolio Planning#Portfolio Components#Strategic Alignment