nerdexam
PMI

PFMP · Question #395

Your company acquired another company. The sponsor asked you to check the other company's current inventory of work and see what could be added to your current portfolio. You have a meeting coming…

The correct answer is A. Portfolio Roadmap. The Portfolio Roadmap is the document that shows the chronological sequencing and dependencies of portfolio components, making it the right artifact to present to a sponsor.

Strategic Alignment

Question

Your company acquired another company. The sponsor asked you to check the other company's current inventory of work and see what could be added to your current portfolio. You have a meeting coming up to show the sponsor the portfolio dependencies. Which document should you be showing him?

Options

  • APortfolio Roadmap
  • BPortfolio Charter
  • CPortfolio Management Plan
  • DPortfolio Strategic Plans of both, your portfolio and the ones of the other company

How the community answered

(51 responses)
  • A
    73% (37)
  • B
    2% (1)
  • C
    8% (4)
  • D
    18% (9)

Why each option

The Portfolio Roadmap is the document that shows the chronological sequencing and dependencies of portfolio components, making it the right artifact to present to a sponsor.

APortfolio RoadmapCorrect

The Portfolio Roadmap is a chronological representation of portfolio components that explicitly shows dependencies, milestones, and the timeline of work, making it the ideal document for demonstrating how acquired work interrelates with existing portfolio components. When a sponsor needs to understand portfolio dependencies, the roadmap provides the visual, dependency-driven view required.

BPortfolio Charter

The Portfolio Charter formally authorizes the portfolio and defines its high-level scope but does not provide a visual representation of component dependencies or sequencing.

CPortfolio Management Plan

The Portfolio Management Plan describes policies, procedures, and processes for managing the portfolio but does not show component-level dependencies and timelines visually.

DPortfolio Strategic Plans of both, your portfolio and the ones of the other company

Portfolio Strategic Plans define vision and strategic objectives for each portfolio but do not depict inter-component dependencies in a way useful for a sponsor overview meeting.

Concept tested: Portfolio Roadmap as component dependency visualization

Source: https://www.pmi.org/pmbok-guide-standards/foundational/standard-for-portfolio-management

Topics

#Portfolio Roadmapping#Portfolio Dependencies#Portfolio Strategic Planning#Portfolio Integration

Community Discussion

No community discussion yet for this question.

Full PFMP Practice