PFMP · Question #364
You have been recently assigned to manage a new portfolio that is supposed to shift the company from silo-based to a projectized one. You are in the process of initiating the portfolio. You are…
The correct answer is B. Portfolio Strategic Plan and Portfolio. The 'Develop Portfolio Strategic Plan' process produces two key outputs: the Portfolio Strategic Plan itself and the Portfolio Charter. Answer B ('Portfolio Strategic Plan and Portfolio [Charter]') reflects this, though the choice text is truncated. The Portfolio Charter is…
Question
You have been recently assigned to manage a new portfolio that is supposed to shift the company from silo-based to a projectized one. You are in the process of initiating the portfolio. You are currently developing the strategic plan. Upon finishing it, you are expected to present
Options
- APortfolio Strategic Plan and Portfolio Process Assets updates
- BPortfolio Strategic Plan and Portfolio
- CPortfolio Strategic Plan
- DPortfolio Strategic Plan and Inventory of Work
How the community answered
(42 responses)- A12% (5)
- B79% (33)
- C5% (2)
- D5% (2)
Explanation
The 'Develop Portfolio Strategic Plan' process produces two key outputs: the Portfolio Strategic Plan itself and the Portfolio Charter. Answer B ('Portfolio Strategic Plan and Portfolio [Charter]') reflects this, though the choice text is truncated. The Portfolio Charter is created or updated as a direct result of developing the strategic plan because the charter formally authorizes the portfolio and aligns it with the strategic direction just established. Option A incorrectly includes 'Portfolio Process Assets updates' as a primary output. Option C (only the Strategic Plan) is incomplete. Option D (Strategic Plan and Inventory of Work) confuses this with a different process output.