PFMP · Question #355
One of your team members who is particularly interested in becoming a portfolio manager has asked you what is the relation between the Portfolio roadmap and the Programs/Projects roadmaps? What…
The correct answer is A. Program and Project roadmaps may be included in the portfolio roadmap. The portfolio roadmap is the highest-level roadmap and may incorporate program and project roadmaps as component-level detail within it. They are hierarchically related, not independent.
Question
One of your team members who is particularly interested in becoming a portfolio manager has asked you what is the relation between the Portfolio roadmap and the Programs/Projects roadmaps? What should be your answer to him?
Options
- AProgram and Project roadmaps may be included in the portfolio roadmap
- BThere is no relation whatsoever
- CProgram and Project roadmaps are more detailed and less strategically aligned
- DPortfolio roadmaps are high level approaches for program and project roadmaps
How the community answered
(26 responses)- A88% (23)
- B8% (2)
- D4% (1)
Why each option
The portfolio roadmap is the highest-level roadmap and may incorporate program and project roadmaps as component-level detail within it. They are hierarchically related, not independent.
According to the PMI Standard for Portfolio Management, program and project roadmaps represent lower-level detail and may be included within the portfolio roadmap as supporting sub-documents. The portfolio roadmap provides the strategic sequencing of components, and individual component roadmaps can be embedded to show more granular timelines.
There is a direct hierarchical relationship between portfolio, program, and project roadmaps - they are aligned to the same strategic objectives at different levels of detail.
While program and project roadmaps are more detailed, this choice fails to accurately describe the relationship - it does not address whether one is included in or derived from the other.
The portfolio roadmap does not serve as a high-level approach for developing program/project roadmaps; rather, those roadmaps may be included within it, not derived from it procedurally.
Concept tested: Relationship between portfolio and component roadmaps
Source: https://www.pmi.org/pmbok-guide-standards/foundational/portfolio-management