nerdexam
PMI

PFMP · Question #339

One of your components within the portfolio has been struggling and has undertaken a lot of issues. A recent measurement has shown that its CPI is 0.4 and SPI is 0.3. What is the best course of action

The correct answer is C. Request that the component governance board checks this component and takes a decision on. With a CPI of 0.4 and SPI of 0.3 indicating critical underperformance, the portfolio manager should escalate to the component governance board for a formal review and decision rather than acting unilaterally.

Portfolio Governance

Question

One of your components within the portfolio has been struggling and has undertaken a lot of issues. A recent measurement has shown that its CPI is 0.4 and SPI is 0.3. What is the best course of action you should take as a portfolio manager

Options

  • AEscalate the issue to the Portfolio steering committee
  • BImmediately terminate the component
  • CRequest that the component governance board checks this component and takes a decision on
  • DNotify the sponsor of the component about the issue

How the community answered

(23 responses)
  • A
    4% (1)
  • B
    13% (3)
  • C
    74% (17)
  • D
    9% (2)

Why each option

With a CPI of 0.4 and SPI of 0.3 indicating critical underperformance, the portfolio manager should escalate to the component governance board for a formal review and decision rather than acting unilaterally.

AEscalate the issue to the Portfolio steering committee

Escalating directly to the Portfolio Steering Committee skips the component-level governance structure; the component governance board should conduct its review and act first before any escalation proceeds further up the hierarchy.

BImmediately terminate the component

Immediate termination is a unilateral action that exceeds the portfolio manager's authority and bypasses the required governance decision-making processes that must precede such a significant action.

CRequest that the component governance board checks this component and takes a decision onCorrect

The portfolio manager's role is governance oversight and escalation, not direct management of component-level execution decisions. A CPI of 0.4 and SPI of 0.3 represent severe cost and schedule overruns that require a formal governance review - such as replanning, restructuring, or termination - which falls within the component governance board's decision-making authority.

DNotify the sponsor of the component about the issue

Notifying the sponsor alone is insufficient given the severity of the performance data - a formal governance board review and decision is required, and the sponsor notification should accompany that process, not replace it.

Concept tested: Portfolio governance escalation for critically underperforming components

Source: https://www.pmi.org/pmbok-guide-standards/foundational/standard-for-portfolio-management

Topics

#Portfolio Governance#Earned Value Management (EVM)#Portfolio Performance Management#Decision Making

Community Discussion

No community discussion yet for this question.

Full PFMP Practice