PFMP · Question #339
One of your components within the portfolio has been struggling and has undertaken a lot of issues. A recent measurement has shown that its CPI is 0.4 and SPI is 0.3. What is the best course of action
The correct answer is C. Request that the component governance board checks this component and takes a decision on. With a CPI of 0.4 and SPI of 0.3 indicating critical underperformance, the portfolio manager should escalate to the component governance board for a formal review and decision rather than acting unilaterally.
Question
One of your components within the portfolio has been struggling and has undertaken a lot of issues. A recent measurement has shown that its CPI is 0.4 and SPI is 0.3. What is the best course of action you should take as a portfolio manager
Options
- AEscalate the issue to the Portfolio steering committee
- BImmediately terminate the component
- CRequest that the component governance board checks this component and takes a decision on
- DNotify the sponsor of the component about the issue
How the community answered
(23 responses)- A4% (1)
- B13% (3)
- C74% (17)
- D9% (2)
Why each option
With a CPI of 0.4 and SPI of 0.3 indicating critical underperformance, the portfolio manager should escalate to the component governance board for a formal review and decision rather than acting unilaterally.
Escalating directly to the Portfolio Steering Committee skips the component-level governance structure; the component governance board should conduct its review and act first before any escalation proceeds further up the hierarchy.
Immediate termination is a unilateral action that exceeds the portfolio manager's authority and bypasses the required governance decision-making processes that must precede such a significant action.
The portfolio manager's role is governance oversight and escalation, not direct management of component-level execution decisions. A CPI of 0.4 and SPI of 0.3 represent severe cost and schedule overruns that require a formal governance review - such as replanning, restructuring, or termination - which falls within the component governance board's decision-making authority.
Notifying the sponsor alone is insufficient given the severity of the performance data - a formal governance board review and decision is required, and the sponsor notification should accompany that process, not replace it.
Concept tested: Portfolio governance escalation for critically underperforming components
Source: https://www.pmi.org/pmbok-guide-standards/foundational/standard-for-portfolio-management
Topics
Community Discussion
No community discussion yet for this question.