PFMP · Question #332

As a portfolio manager you visit and re-do the Optimize Portfolio process continuously. Which of the following, in your opinion, is the objective/purpose of the Optimize Portfolio Process?

The correct answer is A. Balance the portfolio for performance and value delivery. The primary objective of the Optimize Portfolio process in PMI portfolio management is to balance portfolio components to maximize performance and value delivery against strategic objectives.

Strategic Alignment

Question

As a portfolio manager you visit and re-do the Optimize Portfolio process continuously. Which of the following, in your opinion, is the objective/purpose of the Optimize Portfolio Process?

Options

  • ABalance the portfolio for performance and value delivery
  • BMake Governance Decisions
  • CCreate an up-to-date list of qualified portfolio component
  • DAllocating resources to develop component proposals or execute portfolio components

How the community answered

(55 responses)
  • A
    93% (51)
  • B
    2% (1)
  • C
    4% (2)
  • D
    2% (1)

Why each option

The primary objective of the Optimize Portfolio process in PMI portfolio management is to balance portfolio components to maximize performance and value delivery against strategic objectives.

ABalance the portfolio for performance and value deliveryCorrect

The Optimize Portfolio process is specifically designed to balance portfolio components across competing dimensions such as risk, return, and resource utilization to ensure the portfolio delivers maximum strategic value. Balancing and optimizing the component mix is what distinguishes this process from other portfolio management activities.

BMake Governance Decisions

Making governance decisions is the purpose of the Portfolio Governance Management process, not the Optimize Portfolio process.

CCreate an up-to-date list of qualified portfolio component

Creating an up-to-date list of qualified components is an output of the Identify Portfolio Components process, not the Optimize Portfolio process.

DAllocating resources to develop component proposals or execute portfolio components

Allocating resources to develop proposals or execute components is the focus of the Manage Portfolio process, not optimization.

Concept tested: Optimize Portfolio process objective in PMI standard

Source: https://www.pmi.org/pmbok-guide-standards/foundational/standard-for-portfolio-management

Topics

#Portfolio Optimization#Portfolio Management Processes#Value Delivery#Strategic Alignment