PFMP · Question #293
You are mid-way through your portfolio and you are approaching a major milestone where multiple components will be authorized for execution and implementation. For informed decision making, as a portf
The correct answer is D. Resources, Assets and governance decisions. The Authorize Portfolio process generates and updates reports related to Resources, Assets, and Governance Decisions. This makes sense because authorization is the formal approval process - when components are authorized, decisions about resource allocation, organizational assets
Question
You are mid-way through your portfolio and you are approaching a major milestone where multiple components will be authorized for execution and implementation. For informed decision making, as a portfolio manager, you will be communicating reports that will be viewed and analyzed, and used as critical information for taking a decision for the authorization of components. After passing through the authorization process, multiple reports are generated and others are updated. What type of reports is generated from this process?
Options
- APerformance
- BResources
- CValue
- DResources, Assets and governance decisions
How the community answered
(63 responses)- A6% (4)
- B3% (2)
- C11% (7)
- D79% (50)
Explanation
The Authorize Portfolio process generates and updates reports related to Resources, Assets, and Governance Decisions. This makes sense because authorization is the formal approval process - when components are authorized, decisions about resource allocation, organizational assets being committed, and governance approvals are the primary outputs documented. Performance reports and Value reports are outputs of other processes such as Monitor and Control Portfolio Performance, not specifically the authorization process itself.
Topics
Community Discussion
No community discussion yet for this question.