PFMP · Question #281

Your portfolio management team is a bit confused about the order of steps to follow when defining a portfolio. They have been having debates and they came to you asking for the correct order of steps

The correct answer is D. Identification, categorization, scoring, ranking, selection, prioritization, resource allocation. According to PMI's Standard for Portfolio Management, the correct sequential steps for portfolio component selection are: (1) Identification – discovering and gathering potential portfolio components; (2) Categorization – grouping components into relevant categories aligned…

Strategic Alignment

Question

Your portfolio management team is a bit confused about the order of steps to follow when defining a portfolio. They have been having debates and they came to you asking for the correct order of steps

Options

  • AIdentification, categorization, ranking, scoring, selection, prioritization, resource allocation
  • BIdentification, categorization, scoring, ranking, prioritization, selection, resource allocation
  • CIdentification, selection, categorization, scoring, ranking, prioritization, resource allocation
  • DIdentification, categorization, scoring, ranking, selection, prioritization, resource allocation

How the community answered

(31 responses)
  • A
    3% (1)
  • B
    6% (2)
  • D
    90% (28)

Explanation

According to PMI's Standard for Portfolio Management, the correct sequential steps for portfolio component selection are: (1) Identification – discovering and gathering potential portfolio components; (2) Categorization – grouping components into relevant categories aligned with strategy; (3) Scoring – evaluating each component against predefined strategic criteria and scoring them; (4) Ranking – ordering components relative to one another based on their scores; (5) Selection – deciding which ranked components will be included in the portfolio; (6) Prioritization – establishing the relative priority among the selected components; and (7) Resource Allocation – assigning available organizational resources to the prioritized components. Option D reflects this exact sequence. The common mistake is confusing the order of scoring/ranking and selection/prioritization, or placing selection before scoring, as seen in the incorrect options.

Topics

#Portfolio Definition Process#Portfolio Optimization#Strategic Alignment#Component Selection