PFMP · Question #276

Companies adopt project, program and portfolio management practices to enable the realization of business value and the achievement of strategies and objectives. In order to advance the organizational

The correct answer is A. Strengthen the organizational enablers such as cultural, technological and human resource. To advance organizational capability and align portfolio, program, and project management practices, companies must strengthen organizational enablers including cultural, technological, and human resource factors.

Strategic Alignment

Question

Companies adopt project, program and portfolio management practices to enable the realization of business value and the achievement of strategies and objectives. In order to advance the organizational capability and facilitate the alignment of these practices, the company should (choose the best answer)

Options

  • AStrengthen the organizational enablers such as cultural, technological and human resource
  • BPerform a detailed strategic planning
  • CEstablish a PMO to support those practices
  • DStrengthen the processes and procedures of project, program and portfolio management

How the community answered

(41 responses)
  • A
    71% (29)
  • B
    5% (2)
  • C
    7% (3)
  • D
    17% (7)

Why each option

To advance organizational capability and align portfolio, program, and project management practices, companies must strengthen organizational enablers including cultural, technological, and human resource factors.

AStrengthen the organizational enablers such as cultural, technological and human resourceCorrect

Organizational enablers are the structural, cultural, technological, and human resource practices that support effective portfolio, program, and project management. Strengthening these enablers creates an environment where management practices can flourish and remain aligned to business strategy. PMI's frameworks emphasize that without robust organizational enablers, even well-defined processes and PMOs will fail to deliver consistent value.

BPerform a detailed strategic planning

Strategic planning is a critical activity but alone does not advance the organizational capability needed to sustain portfolio management practices.

CEstablish a PMO to support those practices

Establishing a PMO is one structural mechanism but addresses only part of the organizational capability needed and is not sufficient on its own.

DStrengthen the processes and procedures of project, program and portfolio management

Strengthening processes and procedures is important but represents only one dimension of organizational capability, excluding cultural and human resource factors.

Concept tested: Organizational enablers for portfolio management capability

Source: https://www.pmi.org/pmbok-guide-standards/foundational/standard-for-portfolio-management

Topics

#Organizational Capability#Strategic Alignment#Organizational Enablers#Portfolio Management Practices