nerdexam
PMI

PFMP · Question #260

When assessing a portfolio's level of risk, which organizational levels should a portfolio manager focus on for input?

The correct answer is A. Project teams, program teams, external stakeholders, and internal stakeholders. A comprehensive portfolio risk assessment requires input from all levels of stakeholder involvement. Project teams and program teams provide ground-level execution risk data. Internal stakeholders offer organizational and operational risk perspectives. External stakeholders surfa

Portfolio Risk Management

Question

When assessing a portfolio's level of risk, which organizational levels should a portfolio manager focus on for input?

Options

  • AProject teams, program teams, external stakeholders, and internal stakeholders
  • BProject teams, program teams, vendors, and internal stakeholders
  • CExecutive management, operations management, portfolio management, and program teams
  • DCustomers, vendors, sponsors, and program teams

How the community answered

(52 responses)
  • A
    90% (47)
  • B
    6% (3)
  • C
    2% (1)
  • D
    2% (1)

Explanation

A comprehensive portfolio risk assessment requires input from all levels of stakeholder involvement. Project teams and program teams provide ground-level execution risk data. Internal stakeholders offer organizational and operational risk perspectives. External stakeholders surface market, regulatory, and third-party risks. Option A covers this full spectrum. Option B replaces external stakeholders with vendors, which is too narrow and excludes customers, regulators, and other external parties. Option C focuses only on management levels, missing execution-level teams. Option D focuses on customers, vendors, and sponsors, omitting the execution teams who have direct visibility into technical and delivery risks.

Topics

#Portfolio Risk Management#Stakeholder Engagement#Risk Input Sources#Organizational Levels

Community Discussion

No community discussion yet for this question.

Full PFMP Practice