nerdexam
PMIPMI

PFMP · Question #206

PFMP Question #206: Real Exam Question with Answer & Explanation

The correct answer is D: D, C, B, A. See the full explanation below for the reasoning.

Portfolio Performance Management

Question

While developing a schedule of portfolio components for proposal to the governance board, a portfolio manager has identified the following priorities of four components: The following component dependencies exist: Component A is dependent on the output of Component B Component B is dependent on the output of Component C Assuming that resource constraints do not allow work to be done on two components in parallel, in which order should the components be listed on the portfolio roadmap?

Options

  • AA, D, B, C
  • BB, C, D, A
  • CD, A, B, C
  • DD, C, B, A

Topics

#Portfolio Scheduling#Component Dependencies#Portfolio Roadmap#Sequential Work

Community Discussion

No community discussion yet for this question.

Full PFMP PracticeBrowse All PFMP Questions