PMIPMI
PFMP · Question #206
PFMP Question #206: Real Exam Question with Answer & Explanation
The correct answer is D: D, C, B, A. See the full explanation below for the reasoning.
Portfolio Performance Management
Question
While developing a schedule of portfolio components for proposal to the governance board, a portfolio manager has identified the following priorities of four components: The following component dependencies exist: Component A is dependent on the output of Component B Component B is dependent on the output of Component C Assuming that resource constraints do not allow work to be done on two components in parallel, in which order should the components be listed on the portfolio roadmap?
Options
- AA, D, B, C
- BB, C, D, A
- CD, A, B, C
- DD, C, B, A
Topics
#Portfolio Scheduling#Component Dependencies#Portfolio Roadmap#Sequential Work
Community Discussion
No community discussion yet for this question.