PFMP · Question #166

Component portfolio management stage-gate reviews are intended for the steering committee to:

The correct answer is A. evaluate component progress based on organizational strategy and objectives.. Stage-gate reviews at the portfolio steering committee level are strategic checkpoints - their primary purpose is to assess whether each component continues to align with and contribute to organizational strategy and objectives. Unlike project-level reviews, they are not focused

Portfolio Governance

Question

Component portfolio management stage-gate reviews are intended for the steering committee to:

Options

  • Aevaluate component progress based on organizational strategy and objectives.
  • Bevaluate component progress based on the component lifecycle.
  • Capprove or reject component change controls.
  • Dselect and reprioritize new components that have been submitted.

How the community answered

(34 responses)
  • A
    88% (30)
  • B
    3% (1)
  • C
    3% (1)
  • D
    6% (2)

Explanation

Stage-gate reviews at the portfolio steering committee level are strategic checkpoints - their primary purpose is to assess whether each component continues to align with and contribute to organizational strategy and objectives. Unlike project-level reviews, they are not focused on detailed lifecycle metrics (B). Approving or rejecting change controls (C) is a governance process, not the main intent of stage-gate reviews. Selecting and reprioritizing new components (D) is a portfolio balancing activity, not the purpose of a stage-gate review on existing components.

Topics

#Portfolio Management#Stage-Gate Reviews#Steering Committee#Strategic Alignment