PFMP · Question #163
Some key stakeholders complain that components are not being initiated, even though it is believed that these components are critical to the organizational strategy. What should the portfolio…
The correct answer is A. Defined and communicated the portfolio prioritization model. The stakeholder complaint reveals a transparency and communication gap. When stakeholders do not understand why certain components are being selected or deprioritized, it means the criteria used to rank and choose components were either unclear or not shared. Defining and…
Question
Some key stakeholders complain that components are not being initiated, even though it is believed that these components are critical to the organizational strategy. What should the portfolio manager have done to avoid this issue?
Options
- ADefined and communicated the portfolio prioritization model
- BModified the portfolio prioritization criteria
- CAdequately managed the supply and demand process
- DAdded the key stakeholders to the portfolio management board
How the community answered
(25 responses)- A76% (19)
- B12% (3)
- C8% (2)
- D4% (1)
Explanation
The stakeholder complaint reveals a transparency and communication gap. When stakeholders do not understand why certain components are being selected or deprioritized, it means the criteria used to rank and choose components were either unclear or not shared. Defining and communicating the prioritization model ensures all stakeholders understand how and why decisions are made, reducing confusion and mistrust. Modifying criteria (B) addresses the wrong problem - the issue is communication, not the criteria themselves. Managing supply and demand (C) addresses resource capacity, not stakeholder understanding. Adding stakeholders to the board (D) is a governance change that does not solve the root communication issue.