Portfolio Risk Management
Question
A supply chain manager mentioned that the required materials for your portfolio might be out of stock next month due to coronavirus. What should you do next?
Options
- AAnalyze the impact on the portfolio
- BContact new vendors to provide materials
- CRecord the risk in a risk register
- DMention the risk in risk reports