PFMP · Question #11
Which of the following should be included in a portfolio risk management plan? (Choose two.)
The correct answer is B. Methodology C. Roles and responsibilities. A portfolio risk management plan describes how risk management will be structured and performed. It specifically includes the methodology (the approach, tools, and data sources used to perform risk management) and roles and responsibilities (who leads, supports, and participates
Question
Which of the following should be included in a portfolio risk management plan? (Choose two.)
Options
- ADependencies
- BMethodology
- CRoles and responsibilities
- DKey milestones and deliverables
How the community answered
(38 responses)- A3% (1)
- B95% (36)
- D3% (1)
Explanation
A portfolio risk management plan describes how risk management will be structured and performed. It specifically includes the methodology (the approach, tools, and data sources used to perform risk management) and roles and responsibilities (who leads, supports, and participates in risk management activities). Dependencies (A) and key milestones and deliverables (D) are components of the portfolio management plan or roadmap, not the risk management plan.
Topics
Community Discussion
No community discussion yet for this question.