PC0-003 · Question #128
PC0-003 Question #128: Real Exam Question with Answer & Explanation
The correct answer is C. Business Change -> Outcome -> Intermediate Benefit. See the full explanation below for the reasoning.
Question
Part of the project output to the strategic objective chain is in which order?
Options
- AEnd Benefit -> Outcome -> Business Change
- BBusiness Change -> End Benefit -> Outcome
- CBusiness Change -> Outcome -> Intermediate Benefit
- DOutcome -> Business Change -> Intermediate Benefit