Part of the project output to the strategic objective chain is in which order?

The correct answer is C. Business Change -> Outcome -> Intermediate Benefit. See the full explanation below for the reasoning.

Question

Part of the project output to the strategic objective chain is in which order?

Options

  • AEnd Benefit -> Outcome -> Business Change
  • BBusiness Change -> End Benefit -> Outcome
  • CBusiness Change -> Outcome -> Intermediate Benefit
  • DOutcome -> Business Change -> Intermediate Benefit

How the community answered

(52 responses)
  • A
    10% (5)
  • B
    2% (1)
  • C
    83% (43)
  • D
    6% (3)