Why are programme governance baselines updated?
The correct answer is A. Reflect lessons learned, in Managing the Tranches. See the full explanation below for the reasoning.
Question
Why are programme governance baselines updated?
Options
- AReflect lessons learned, in Managing the Tranches
- BAdjust programme governance to align with project governance, in Delivering the Capability
- CReflect lessons from earlier programmes, in Identifying a Programme
- DPrepare for benefit reviews, in Realizing the Benefits
How the community answered
(30 responses)- A73% (22)
- B7% (2)
- C3% (1)
- D17% (5)