Which describes dependencies that are external to an organization's programme and project environment?

The correct answer is C. Resulting from government decisions to change legislation. See the full explanation below for the reasoning.

Question

Which describes dependencies that are external to an organization's programme and project environment?

Options

  • APart of the governance of the corporate portfolio
  • BWithin the control of the programme itself
  • CResulting from government decisions to change legislation
  • DResulting from relationships between the projects within the Projects Dossier

How the community answered

(17 responses)
  • A
    6% (1)
  • B
    18% (3)
  • C
    71% (12)
  • D
    6% (1)

Community Discussion

No community discussion yet for this question.

Full PC0-003 Practice