Which of the following is NOT a principle of programme risk management?

The correct answer is B. Capture all project risks centrally. See the full explanation below for the reasoning.

Question

Which of the following is NOT a principle of programme risk management?

Options

  • AUnderstand the programme context Risk change
  • BCapture all project risks centrally
  • CInvolve stakeholders
  • DMonitor for early warning indicators

How the community answered

(25 responses)
  • A
    12% (3)
  • B
    80% (20)
  • C
    4% (1)
  • D
    4% (1)