Which statement about emergency changes is CORRECT?
The correct answer is B. The assessment and authorization of emergency changes is expedited to ensure they can be. See the full explanation below for the reasoning.
Question
Which statement about emergency changes is CORRECT?
Options
- AThe testing of emergency can be eliminated in order to implement the change quickly
- BThe assessment and authorization of emergency changes is expedited to ensure they can be
- CEmergency changes should be authorized and implemented as service requests
- DEmergency changes must be fully documented before authorization and implementation
How the community answered
(23 responses)- A13% (3)
- B74% (17)
- C9% (2)
- D4% (1)