PC0-001 · Question #597
When should a full risk assessment and authorization be carried out for a standard change?
The correct answer is B. When the procedure for the standard change is created. See the full explanation below for the reasoning.
Question
When should a full risk assessment and authorization be carried out for a standard change?
Options
- AEach time the standard change is implemented
- BWhen the procedure for the standard change is created
- CAt least once a year
- DWhen an emergency change is requested
How the community answered
(58 responses)- A2% (1)
- B84% (49)
- C3% (2)
- D10% (6)