PC0-001 · Question #597

When should a full risk assessment and authorization be carried out for a standard change?

The correct answer is B. When the procedure for the standard change is created. See the full explanation below for the reasoning.

Question

When should a full risk assessment and authorization be carried out for a standard change?

Options

  • AEach time the standard change is implemented
  • BWhen the procedure for the standard change is created
  • CAt least once a year
  • DWhen an emergency change is requested

How the community answered

(58 responses)
  • A
    2% (1)
  • B
    84% (49)
  • C
    3% (2)
  • D
    10% (6)