How does a P3O model increase an organization's ability to deliver its strategy?
The correct answer is C. Provides decision support to ensure the right projects are launched. See the full explanation below for the reasoning.
Question
How does a P3O model increase an organization's ability to deliver its strategy?
Options
- AEnsures current projects are unaffected by changes to policy or strategy
- BEnables projects to efficiently develop their own financial processes
- CProvides decision support to ensure the right projects are launched
- DAllows senior managers to delegate their governance responsibilities
How the community answered
(30 responses)- A7% (2)
- B13% (4)
- C77% (23)
- D3% (1)
Community Discussion