P3OF · Question #47

Which is needed when getting the investment for a P3O?

The correct answer is D. Recognition of the need for change. See the full explanation below for the reasoning.

Question

Which is needed when getting the investment for a P3O?

Options

  • AIndependence of assurance services
  • BDefined portfolio of change
  • CProvision of secretariat services
  • DRecognition of the need for change

How the community answered

(37 responses)
  • A
    3% (1)
  • B
    16% (6)
  • C
    8% (3)
  • D
    73% (27)