P3OF · Question #147

P3OF Question #147: Real Exam Question with Answer & Explanation

The correct answer is A. Removes barriers to project delivery caused by lack of resource capacity. See the full explanation below for the reasoning.

Question

What benefit is provided by the capacity planning for resource management technique?

Options

  • ARemoves barriers to project delivery caused by lack of resource capacity
  • BProvides the relative priority against which to allocate resources to projects
  • CAllows individual resources to identify what development they require
  • DConnects individuals to allow information to flow between resources