Which technique is used to determine the appropriate level of governance for a project?

The correct answer is C. Complexity modelling. See the full explanation below for the reasoning.

Question

Which technique is used to determine the appropriate level of governance for a project?

Options

  • ABusiness process swimlanes
  • BCapacity planning for resource management
  • CComplexity modelling
  • DSkills development and maintenance

How the community answered

(47 responses)
  • A
    6% (3)
  • B
    4% (2)
  • C
    72% (34)
  • D
    17% (8)