EXIN
P3OF · Question #32
Which describes embedded resources delivering finance functions assigned to a temporary Programme Office?
The correct answer is D. Processes that they will follow are controlled by the finance department. See the full explanation below for the reasoning.
Question
Which describes embedded resources delivering finance functions assigned to a temporary Programme Office?
Options
- AThey are permanently assigned to a programme or project
- BLine management responsibility for them sits within a Programme Office
- CThey use the standards created by a temporary Programme Office
- DProcesses that they will follow are controlled by the finance department
How the community answered
(18 responses)- A6% (1)
- B17% (3)
- C6% (1)
- D72% (13)
Community Discussion