nerdexam
IBM

P2090-027 · Question #9

Using InfoSphere Warehouse Design Studio, how do you propagate the changes that you made in your project?

The correct answer is D. by comparing and synchronizing the project and the original database. See the full explanation below for the reasoning.

Question

Using InfoSphere Warehouse Design Studio, how do you propagate the changes that you made in your project?

Options

  • Aby comparing your source database with the target database
  • Bby reverse engineering the project
  • Cby generating and running a DML script
  • Dby comparing and synchronizing the project and the original database

How the community answered

(16 responses)
  • A
    6% (1)
  • B
    6% (1)
  • C
    19% (3)
  • D
    69% (11)

Community Discussion

No community discussion yet for this question.

Full P2090-027 Practice