In a control flow, the Start operator has an on-failure port. When are any operators linked to that port executed?

The correct answer is B. At the end of a control flow, if there were any on-failure actions processed by any control flow. See the full explanation below for the reasoning.

Question

In a control flow, the Start operator has an on-failure port. When are any operators linked to that port executed?

Options

  • AIf there is an error starting the control flow.
  • BAt the end of a control flow, if there were any on-failure actions processed by any control flow
  • CEach time an on-failure action is processed by a control flow operator.
  • DOnly after designated control flow operators process on-failure actions.

How the community answered

(18 responses)
  • A
    11% (2)
  • B
    78% (14)
  • C
    6% (1)
  • D
    6% (1)