P2090-027 · Question #8
A physical database model was reverse engineered from an existing DB2 database. Several changes were then made to the physical model. Which Design Studio feature would be used to synchronize the…
The correct answer is C. Compare with original source. See the full explanation below for the reasoning.
Question
A physical database model was reverse engineered from an existing DB2 database. Several changes were then made to the physical model. Which Design Studio feature would be used to synchronize the physical model with the actual database?
Options
- AAnalyze impact.
- BCompare with another data object.
- CCompare with original source.
- DCompare with each other.
How the community answered
(43 responses)- A9% (4)
- B5% (2)
- C84% (36)
- D2% (1)